Our previous estimate of production on Betzy has proved to be somewhat optimistic. 

With the help of the vendor, we believe we have identified and fixed the cause of the interconnect stability problem on Betzy. The most recent validation benchmarks have been stable, and we will begin the site acceptance test (SAT) within Friday, 6 November. If the machine passes the SAT, it will be handed over to the operations and opened for production. 

The final preparations usually take 1-3 days. We therefore estimate that production will begin on Betzy within next week, week 46.

Best regards,