Saga security patching from 2025-12-01 06:00 CET to 2025-12-05 21:59 CET
Scheduled maintenance
High Performance Computing
Saga
2025-12-01 06:00 CET
· 4 days, 15 hours, 59 minutes
Updates
Resolved
December 5, 2025 · 21:58 CET
The upgrade has now been completed, and saga is back up.
Thank you very much for your patience!
/NRIS Team
Update
December 5, 2025 · 14:54 CET
Dear users,
We are mostly done with the upgrade, and are close to finishing (majority of the remaining processes are testing/benchmarking and quality assurance related). We will therefore push the planned end-time to 20:00.
Apologies for the inconvenience this might cause!
Scheduled
November 27, 2025 · 15:20 CET
Due to essential security requirements, we must perform a downtime on the Saga cluster next week.
Work to be performed:
- Full patching of Saga
- Firmware upgrade
- Operating system upgrade
- Cluster file system major upgrade
- New Cuda versions
- Security patches
We sincerely apologize for the short notice regarding this downtime.