Planned downtime: Reduced capacity Saga from 2023-06-09 12:00 CEST to 2023-06-16 12:00 CEST
Updates
This maintenance has been concluded as planned.
We have now been able to start up some compute, bigmem and gpu nodes and run jobs on them.
Unfortunately, reducing the capacity by turning off ~ half of the compute nodes was not enough, so we have had to requeue all running jobs and turn off the rest of the compute nodes.
This maintenance is now starting as planned.
We are upgrading backup power for our datacenter in Trondheim. This will affect capacity on Saga and possibly Betzy Between June 9th and June 16th. We will reduce capacity on Saga with at least 50% during these days. This period will transition into a period of three days of downtime for both Saga and Betzy (see other event), from 19th both systems will run with full capacity, but without backup power.